Bedroom sun tunnels (Page 4)
Second weekend
So its been a week now; as we are only able to work on this subject during the weekend. The next thing to do was to finish off the exterior part, as the hip tiles were not cemented down. This meant potentially they could fly off if we had extremely high winds. This took longer than expect, due to the weather - it was pretty much raining non-stop during Saturday. So it took until Sunday morning to be finished;So with afternoon left, we made a start on the interior. The first thing to do was to work out were the sun-tunnels would be. Ideally we wanted them centre of room; however due to situation of the roof, this meant they had to go off-centre and fairly close together;
Hopefully by the end of next weekend we should have the two tunnels complete - apart from finishing-off in the roof area (above).